Steel Building Assembly Guide

What to Have Ready Before Your Assembly Crew Arrives

A smooth assembly starts with a ready site. This guide covers what the customer provides before the crew mobilizes, what is and is not included in assembly, and how AM Star Construction can observe the work at key stages. Assembly is done per the enhanced assembly drawings, not the permit set.

Assembly at a glance

What to know before the assembly crew arrives
Topic Details
Drawings used Assembly follows the enhanced assembly drawings, not the permit set
Who assembles A certified manufacturer's assembly contractor with 5 years of experience
Customer provides Foundation and anchor bolts, a slab and 25 foot perimeter clear of obstructions, a graded and compacted site, a perimeter ramp, drainage, permits, site security, sanitary facilities and power for hand tools
Not included in assembly Field welding and touch up of shop transportation primer, cleaning scuff marks and dirt, and prevailing wage or certified payroll reporting
Observation Engineering observation and certification by AM Star at $1,500 per visit, with at least 3 site visits recommended: before the concrete pour, before paneling and at completion
Restricted site access Increases the assembly contract price for rigging and labor

Customer Responsibilities Before Mobilization

The end customer makes sure the site is ready for assembly before the crew arrives. Here is what that includes.

Foundation and anchor bolts

  • Anchor bolt locations and templates follow the enhanced assembly drawings and the concrete foundation drawings.

Slab and unloading area

  • The slab and a 25 foot perimeter are clear of obstructions for assembly of the steel.
  • The building is unloaded next to the slab. Moving materials twice adds an extra charge for inefficiency.
  • The slab is clear of obstructions and equipment before and during steel assembly.
  • A dumpster or stockpile location for packing materials and scrap is within 25 feet of the slab.

Site conditions and access

  • The site is graded flat and compacted for a two wheel forklift and scissor lift. Lifts will not work on soft and uneven ground.
  • A perimeter ramp is provided to drive onto the slab.
  • Drainage measures keep the site accessible.
  • Clear access and unobstructed work hours are provided.
  • Trees, plants and brush are cleared. The assembly contractor is not responsible for damage to existing concrete, asphalt, hardscape, softscape or underground utilities. Nonskid tires are not included in assembly.

Delivery and site safety

  • The customer is on site to confirm the bill of lading and that no damage or shortages are present.
  • The site is secured by fence, including public walkways, with barricades and other safety measures in place.
  • Delivered materials belong to the customer. Theft and damage from the job site are out of the assembly contractor’s control.
  • Sanitary facilities are provided on site for workers.
  • An electric power source is provided for hand tools.

Permits and standards

  • Building permits are obtained and special inspection requirements are in place.
  • All MBMA codes of standard practice are followed.
  • Normal standards of sequencing are allowed for the best performance.
  • A certified manufacturer’s assembly contractor with 5 years of experience must be used to install the building and components.

Access and pricing

  • Restricted site access increases the assembly contract price for rigging and labor.
  • No prevailing wage requirements or certified payroll reporting are included in assembly.
Request an Assembly Quote

What Is and Is Not Included in Assembly

Site grading and formwork prepared before steel building slab pour

Know the Scope Before You Start

Assembly follows the enhanced assembly drawings, not the permit set. These items are outside the assembly scope or limited by it, so plan for them early.

Request an Assembly Quote

Construction Observation Services

AM Star Construction recommends that these items be verified before moving on to the next step.

Five Observation Checkpoints

Anchor rod and bolt verification

Check the anchor rods and bolts against the drawings.

Main frame and secondary frames

Verify the primary and secondary framing.

Wall sheeting

Verify the wall sheeting.

Roof sheeting

Verify the roof sheeting.

Final observation inspection

A final observation when the work is complete.

All structural work requires engineering observation and certification by AM Star at $1,500 per visit. At least 3 site visits are recommended for quality control: before the concrete pour, before paneling and at completion. Project manager fees are $1,750 per visit for each item, and ongoing administration fees are on a time and materials basis.

Related Butler Building Guides

Read the Builder’s Guide, follow the manufacturer’s installation steps, or plan your slab with the steel foundation guide.

Construction worker assembles metal frame of building on clear sunny day

Frequently Asked Questions

Get in Touch

Email:

Mikeachkar@gmail.com

Phone:

Pro Desk Expert Line: (559) 428-8537

Toll Free Builder Line: (888) 374-2326

Availability:

Available 7 Days a Week from 8am to 5pm and Evenings by Appointment.

Request a New Butler Building Quote

Tell us about your project and we'll put together accurate pricing on a genuine factory-spec Butler building. Every quote is engineer-reviewed and tailored to your building type, size, and timeline.

Thank you! Your request has been submitted — we'll be in touch shortly.

🔒 Your information is secure and never shared. No spam — ever.

Download the Spec Sheet

Fill in the fields below to instantly download your spec sheet. A backup copy will also be sent to your email.

Thank you! Your download has started.

🔒 Your info is safe. No spam — ever.

Seraphinite AcceleratorOptimized by Seraphinite Accelerator
Turns on site high speed to be attractive for people and search engines.