Steel Building Assembly Guide
What to Have Ready Before Your Assembly Crew Arrives
Assembly at a glance
| Topic | Details |
|---|---|
| Drawings used | Assembly follows the enhanced assembly drawings, not the permit set |
| Who assembles | A certified manufacturer's assembly contractor with 5 years of experience |
| Customer provides | Foundation and anchor bolts, a slab and 25 foot perimeter clear of obstructions, a graded and compacted site, a perimeter ramp, drainage, permits, site security, sanitary facilities and power for hand tools |
| Not included in assembly | Field welding and touch up of shop transportation primer, cleaning scuff marks and dirt, and prevailing wage or certified payroll reporting |
| Observation | Engineering observation and certification by AM Star at $1,500 per visit, with at least 3 site visits recommended: before the concrete pour, before paneling and at completion |
| Restricted site access | Increases the assembly contract price for rigging and labor |
Customer Responsibilities Before Mobilization
Foundation and anchor bolts
- Anchor bolt locations and templates follow the enhanced assembly drawings and the concrete foundation drawings.
Slab and unloading area
- The slab and a 25 foot perimeter are clear of obstructions for assembly of the steel.
- The building is unloaded next to the slab. Moving materials twice adds an extra charge for inefficiency.
- The slab is clear of obstructions and equipment before and during steel assembly.
- A dumpster or stockpile location for packing materials and scrap is within 25 feet of the slab.
Site conditions and access
- The site is graded flat and compacted for a two wheel forklift and scissor lift. Lifts will not work on soft and uneven ground.
- A perimeter ramp is provided to drive onto the slab.
- Drainage measures keep the site accessible.
- Clear access and unobstructed work hours are provided.
- Trees, plants and brush are cleared. The assembly contractor is not responsible for damage to existing concrete, asphalt, hardscape, softscape or underground utilities. Nonskid tires are not included in assembly.
Delivery and site safety
- The customer is on site to confirm the bill of lading and that no damage or shortages are present.
- The site is secured by fence, including public walkways, with barricades and other safety measures in place.
- Delivered materials belong to the customer. Theft and damage from the job site are out of the assembly contractor’s control.
- Sanitary facilities are provided on site for workers.
- An electric power source is provided for hand tools.
Permits and standards
- Building permits are obtained and special inspection requirements are in place.
- All MBMA codes of standard practice are followed.
- Normal standards of sequencing are allowed for the best performance.
- A certified manufacturer’s assembly contractor with 5 years of experience must be used to install the building and components.
Access and pricing
- Restricted site access increases the assembly contract price for rigging and labor.
- No prevailing wage requirements or certified payroll reporting are included in assembly.
What Is and Is Not Included in Assembly

Know the Scope Before You Start
Assembly follows the enhanced assembly drawings, not the permit set. These items are outside the assembly scope or limited by it, so plan for them early.
Primer and touch up
Field welding and touch up of shop transportation primer are not part of the scope. Shop coat primer is meant for transportation only. Scratched panels are touched up as part of the normal assembly sequence if required.
Scuff marks and cleaning
Scuff marks or dirt on the steel or slab are not the responsibility of AM Star or Butler. The owner must hire a professional painter to clean and paint the steel as required.
Shortage and damage claims
Material shortage claims and damage to building component claims are limited to replacement of the parts. No liquidated or consequential damages are accepted, and they are considered excusable delay.
Excess materials
Excess materials are the property of the manufacturer or AM Star and are dumped on site or removed.
Engineering drawings
Assembly is done per the enhanced assembly drawings, not the permit set.
Construction Observation Services
AM Star Construction recommends that these items be verified before moving on to the next step.
Five Observation Checkpoints
Anchor rod and bolt verification
Check the anchor rods and bolts against the drawings.
Main frame and secondary frames
Verify the primary and secondary framing.
Wall sheeting
Verify the wall sheeting.
Roof sheeting
Verify the roof sheeting.
Final observation inspection
A final observation when the work is complete.
All structural work requires engineering observation and certification by AM Star at $1,500 per visit. At least 3 site visits are recommended for quality control: before the concrete pour, before paneling and at completion. Project manager fees are $1,750 per visit for each item, and ongoing administration fees are on a time and materials basis.
Observation services notice
AM Star Construction, Inc. provides construction observations for quality assurance purposes only. Such observations are limited and periodic and do not constitute continuous inspection, supervision or verification of the work. The Contractor and Installer retain sole responsibility for ensuring that all work is performed in strict accordance with the approved plans, specifications, shop drawings, engineering requirements, permit conditions, applicable codes and industry standards. Neither the presence nor absence of comments from AM Star Construction, Inc. shall be construed as acceptance of nonconforming work or assumption of responsibility for construction compliance. The Owner expressly releases and holds harmless AM Star Construction from any liability related to project compliance, construction defects or code violations arising from the Contractor’s or Installer’s performance of the work.
Related Butler Building Guides
Read the Builder’s Guide, follow the manufacturer’s installation steps, or plan your slab with the steel foundation guide.

Frequently Asked Questions
Who assembles my Butler Building?
A certified manufacturer’s assembly contractor with 5 years of experience must be used to install the building and components. Ask AM Star Construction about assembly for your project.
What does the customer need to prepare?
The foundation and anchor bolts, a clear and compacted site, a perimeter ramp, drainage, permits, site security, sanitary facilities and power for hand tools. See the list above for the full details.
Do I need permits before assembly?
Yes. Building permits need to be obtained and special inspection requirements need to be in place before assembly.
Why does the site need to be graded and compacted?
The assembly crew uses a two wheel forklift and a scissor lift. Lifts will not work on soft and uneven ground.
What if my site has restricted access?
Restricted site access increases the assembly contract price for rigging and labor. Tell us about your site early so we can plan for it.
How often should the work be observed?
At least 3 site visits are recommended for quality control: before the concrete pour, before paneling and at completion.
Get in Touch
Email:
Mikeachkar@gmail.com
Phone:
Pro Desk Expert Line: (559) 428-8537
Toll Free Builder Line: (888) 374-2326
Availability:
Available 7 Days a Week from 8am to 5pm and Evenings by Appointment.
Request a New Butler Building Quote
Tell us about your project and we'll put together accurate pricing on a genuine factory-spec Butler building. Every quote is engineer-reviewed and tailored to your building type, size, and timeline.
Download the Spec Sheet
Fill in the fields below to instantly download your spec sheet. A backup copy will also be sent to your email.